Veeru Sagar Lake De-silting & Catchment Restoration

Taluk: Chengalpattu · Published 18 Jul 2026 · Last progress update 12 days ago

Removal of 18,000 cubic metres of silt from the 5.2-hectare lake bed, strengthening of bunds, construction of recharge pits and a bio-retention along the outfall channel. Restores irrigation storage for 2,140 farming households in the Velur belt.

Veeru Sagar Lake De-silting & Catchment Restoration

Photographs from the field

Project photograph
Project photograph

Weekly progress reports

  1. Week 4 - De-silting 40% complete

    16 Aug 2026 · 28 days ago
    38% complete

    6,800 cubic metres of silt removed to the designated farm-pond network. Recharge pit excavation started on the eastern bund.

  2. Week 1 - Site survey and bund marking completed

    26 Jul 2026 · 1 month ago
    15% complete

    Topographic survey of the 5.2 ha lake bed completed. Bund alignment marked and approved by the PWD assistant executive engineer. Silt removal tenders floated.