Water & EnvironmentWork in progressRef: CSR/CPC/2026/009
Veeru Sagar Lake De-silting & Catchment Restoration
Taluk: Chengalpattu · Published 18 Jul 2026 · Last progress update 12 days ago
Removal of 18,000 cubic metres of silt from the 5.2-hectare lake bed, strengthening of bunds, construction of recharge pits and a bio-retention along the outfall channel. Restores irrigation storage for 2,140 farming households in the Velur belt.

Photographs from the field

Weekly progress reports
Week 4 - De-silting 40% complete
16 Aug 2026 · 28 days ago38% complete6,800 cubic metres of silt removed to the designated farm-pond network. Recharge pit excavation started on the eastern bund.
Week 1 - Site survey and bund marking completed
26 Jul 2026 · 1 month ago15% completeTopographic survey of the 5.2 ha lake bed completed. Bund alignment marked and approved by the PWD assistant executive engineer. Silt removal tenders floated.